If you have a question
that you don't see listed below, send it via e-mail,
and the answer will be posted on this site.
What is the goal/big picture for construction?
The goal of construction is to recover the Medical School from the devastation
of Tropical Storm Allison and to return it to a state in which it is
better than before. Flood mitigation is also part of the project, which
will prevent the type of damage we incurred in 2001. These goals were
completed in the fall of 2005, yet construction continues as the six-story
Replacement Research Facilitly adjacent to the Medical School Building
takes shape. It will be ready for occupancy in the fall of 2007.
What are the allowable hours for loud construction?
No loud construction should be occurring between 8 a.m. and 5 p.m. during
the work week. This work is supposed to happen before or after “Medical
School Building (MSB) work hours.” No construction noise at all
is allowed on specific examination days as specified by the Medical
School.
Why is construction taking so long?
The recovery and reconstruction for a state-supported medical school
such as ours involves many players and is quite complicated. From our
insurance companies to the federal government (Federal Emergency Management
Agency) and The University of Texas System, much coordination had to
take place in order to get to our present stage of active construction.
Money had to be in hand to start construction, and a FEMA settlement
took some time as did a settlement from our insurance companies. Thanks
also to the support of our Legislature, which provided funding in the
form of tuition revenue bonds in June, construction has ramped up.
As we have made our way into the project, construction plans have chOctober 2, 2006ulted in
delays. But we are confident that this thorough approach will serve
us better than an attempt at a quick fix.
Additionally, once we did start construction, the perimeter
wall was and is considered the critical protection project. Its progress
is constrained by the emergency escapes at the stairwells. We need to
keep six stairwells open at any one time, and therefore the sequence
and timing of the wall “phases” depend on maintaining the
emergency exit strategy of the building. Much of the interior build back,
from the Learning Resource Center, to the Leather Lounge, to the dock
spaces in the basement, then rely on portions of the wall to be complete
before they can be completed, outside to inside. The construction pattern
is an intricately linked sequence.
Last but not least, in trying to preserve a minimally
acceptable work environment, we are balancing the need to work at "off-hours" with
noisy work with a sense of financial accountability that does not spend
excessive dollars on premium or overtime work. This also has an effect
of extending the schedule, when compared to open, full-day, no constraint
construction.
What is the timeline for construction?
- John Freeman Building Classrooms: Complete
- 7 Tesla MRI: Complete
- Electron Microscope: Complete
- Nuclear Magnetic Resonance Spectrometer: Complete
- Ground Floor Office Build Out: Complete
- Learning Resource Center: Complete
- 3T Magnet Complete
- Perimeter Wall (flood protection): Complete
- Gross Anatomy (basement:) Complete
- Vivarium and Replacement Research Facility: Fall 2007
- Surgical and Clinical Skills Center: Spring 2006
Why do the project completion dates change?
Construction is at the mercy of numerous external factors
– such as inclement weather, unforeseen site conditions (buried
utilities not on current building plans), unexpected changes, and funding
issues. These are the types of issues that knock construction timetables
off track, which causes a domino effect – as project A has to be
completed before project B can begin.
What is being done to be sure the school doesn’t
flood again?
Several flood mitigation efforts are being implemented, including the
construction of a granite and aquarium glass wall that will surround
the school, acting as a barrier to water; the installation of flood doors
and gates able to withstand walls of water; the moving of mechanical
equipment above levels that could be flooded; and placing more water-tolerable
offices and other services in vulnerable areas and moving more sensitive
equipment and offices, such as the animals, out of harm’s way.
Where will the animals be located?
The vivarium will be located on the top two stories of the Replacement
Research Facility.
Who is responsible for the construction? Who
can I contact with a concern?
Ultimately this project is being overseen by The University of Texas
System but locally it is a combined effort of the Medical School, the
Office of Facilities and Planning, and various construction companies
and contractors. Click here for
a list of contacts on specific topics.
Will the school be closed during any of the
construction?
No. The construction will not interfere with our missions of education,
patient care, and research.
Is there a fund-raising effort going on to help
the Medical School’s reconstruction?
Yes, there is a fund-raising effort, which aims to raise $14 million
for the Surgical and Clinical Skills Center, which will be a state-of-the
art facility to train, students, residents, physicians, and other health-care
professionals. For more information on how you can help, contact development.
Where can people in wheelchairs go to access
the John Freeman Building from the Medical School without going outside
now that the blue elevators do not go down to the ground floor?
Currently such individuals must go outside when traveling from the Medical
School to the ground floor of the John Freeman Building. Claire
Brunson is working with these individuals to accommodate their needs,
so please contact her directly at 713-500-5018 if you or someone you know has such a
special situation.
|